FastCAM QE - Processed Linear

Part of the QE Training guide

Overview:

This guide explains how to use the Processed Linear option in QE to quote long product

Example Use Case:

This is when you need to quote linear product (Sections / Long Product), and have been given a sheet which describes the lengths & products required for the job. 

1. Accessing Linear Processing

  • Click on the Processed Linear icon to begin.

2. Select Material and Section

  • Choose the appropriate Group Material and Section from the dropdown lists.

3. Input Part Details

  • Fill in the Parts Table with the required information.
    • You should include Mitres and holes in most cases
  • Use the Add Row option to include additional parts as needed.

 

4. Calculate Nest

  • Click Calculate to generate the nest layout.
  • You can also calculate using "Scrap Offcuts" which will prioritize minimizing wastage and not returning anything to stock. 

Note: The scrap amount may increase because of this

5. Adjust Available Stock

  • You can edit the Stock selection window, by either adding lengths, or removing existing lengths. 
  • For example, navigate to the stock section and adjust the available sizes by removing unnecessary entries.

6. Modify Material Sell Pricing

  • You can update the Sell Price of the material using either $/unit or $/tonne.
  • Click Calculate again to see the updated pricing.

 

7. Charge Full Lengths (Optional)

  • For customers who want to purchase full lengths and do the processing of the lengths themselves:
  • Go to the Stock Menu.
  • Select Charge Full Lengths.
  • Click Calculate.
  •  

8. Add Nose Trims and Extra Lengths

If your job is close to the length of a beam, you may need some extra length to allow the calculation (once it includes the cut) to proceed. You can use an Extra Length allowance to cover these cases.

You can also add a Nose trim if needed. 

9. Adjust Process Type

  • You can change the processes selected, to whatever is available, as you see fit. 

10. Customize Process Settings

  • Click on the Process Selection Sprocket to access detailed settings.
  • Pricing adjustments can be made using:
  • - $/hour
  • - $/tonne
  • - $/each
  • Each process category—Cope, Hole, and Cutoff—is listed with standard times and cost configurations.

11. Handling Adjustments

  • Customize Handling values based on job requirements.
  • Be sure the handling reflects the job at hand. If you are doing a lot of small parts, it will likely need different handling to few large parts, and will have to be calculated differently.

(Note: Handling will automatically update.)

12. Add Extra Processes (Optional)

  • Add any Extra Processes that may be required for the line item.

13. Finalize the Line Item

  • Once all settings are complete, click Save to store the processed linear item.
  • The item is now ready to be included in the customer quote.

Is this article helpful?
0 0 0